Weighhouse Street Temporary Site Set Up Scheme

Weighhouse Street Temporary Site Set Up Scheme

Ward: West End

Streets Affected: Weighhouse Street

Project Type: Streetscape

Project Overview

Westminster City Council is reparing the footway pavement

The proposals include the following improvement to the streetscape environment:

  • Taking up existing damaged footway pavement
  • Reinstatement of pavement and levels
  • Installation of two new temporary bollards
The implementation of the streetscape improvements is to commence in early February 2013.

Status

Works completed

Outline Programme

February 2013 - February 2013

Project Documents

STATUS

    On Hold
    Design Stage
    In Consultation
    Works on site
    Works completed