Ward: Churchill
Streets Affected: Buckingham Palace Road, Semley Place
Project Type: Traffic, Safety & Parking
Project Overview
At present vehicles are unable to turn right out of Semley Place into Buckingham Palace Road and TfL (Victoria Coach Station) are seeking to permit right turn manoeuvres at this junction to reduce the journey time for coaches exiting Victoria Coach Scheme. This scheme seeks to amend the junction layout to allow right turn movements from Semley Place. The two-stage pedestrian crossing layout on Buckingham Place Road at this junction will be changed to one-stage pedestrian crossing to shorten the crossing time.
Status
Works completed
Outline Programme
Advanced Signal work starts from 17 October 2015. Construction works will be commenced on 26 October 2015 and to be completed by 7 December 2015.
Project Documents
Semley Place - Scheme Board.pdf - (233 kb)
STATUS
On Hold