Covent Garden Footways - Phase 4 - Southampton Street - Footway Improvements.

Covent Garden Footways - Phase 4 - Southampton Street - Footway Improvements.

Ward: St James's

Streets Affected: Covent Garden, Henrietta Street, Southampton Street, Tavistock Street

Project Type: Streetscape

Project Overview

On the 19th of April 2016, a scheme involving the repaving of the existing footways on
Southampton Street (between Henrietta Street and Tavistock Street) in natural York
stone and the replacement of existing coal hole covers with new bespoke covers will
commence.

This phase of works is to be completed by mid-May 2016.

Status

Works due

Outline Programme

Implementation 19/04/2016-12/05/2016.

Project Documents

There are no documents available for this project

STATUS

    Concept
    Feasibility
    In Consultation
    Design Stage
    Works due
    Works on site
    Works completed