Covent Garden Footways - Phase 6 - Covent Garden (Outside London Transport Museum) - Footway Improve

Covent Garden Footways - Phase 6 - Covent Garden (Outside London Transport Museum) - Footway Improve

Ward: St James's

Streets Affected: Covent Garden

Project Type: Streetscape

Project Overview

On the 26th of May 2016, a scheme involving the repaving of the existing footway on
Covent Garden (immediately outside the London Transport Museum) in natural York
stone will commence.

This phase of works is to be completed by early June 2016.

Status

Works completed

Outline Programme

Implementation 26/05/2016-02/06/2016.

Project Documents

There are no documents available for this project

STATUS

    On Hold
    Design Stage
    In Consultation
    Works on site
    Works completed