Cookie Consent by Free Privacy Policy Generator website

Cycle Superhighway East West Sussex Square

Cycle Superhighway East West Sussex Square

Ward: Hyde Park

Streets Affected: Sussex Square

Project Type: Traffic, Safety & Parking

Project Overview

Design and Implementation of pedestrian crossing improvements at Sussex Square, as part of complementary measures for the East West Cycle Superhighway.  A zebra crossing point is proposed west of Sussex Square (west arm).  As part of this proposal the carriageway is to be narrowed  and raised at the crossing point to improve pedestrian comfort and movement and to slow traffic down along Stanhope Terrace

Status

Works completed

Outline Programme

Start Date: 14 November 2016 Approximate End Date: 16 December 2016

Project Documents

There are no documents available for this project

STATUS

    On Hold
    Design Stage
    In Consultation
    Works on site
    Works completed