North Wharf Gardens Site II Highway Improvements

North Wharf Gardens Site II Highway Improvements

Ward: Hyde Park

Streets Affected: Harrow Road, North Wharf Road

Project Type: Streetscape

Project Overview

FM Conway, on behalf of Westminster City Council, will be carrying out highway improvement works in North Wharf Road and Harrow Road as part of the redevelopment of North Wharf Gardens Site II.

Works will be implemented in two (2) phases:

Phase 1 (residential block towers):

  • a. March 18th – April 19th, 2019; footway adjacent to the development along the south eastern arm of North Wharf Road, and along Harrow Road
  • b. August 2019; North Wharf Road from the development north-western end to approximately 55 meters east;
Phase 2 (Hotel and School):
  • Spring 2021; footway adjacent to the development along the eastern arm of North Wharf Road, and along Harrow Road from its junction with North Wharf Road to approximately 70 meters west. Also, improvement works will be undertaken to the Harrow Road central island.

improvements include the following:
  • New kerbing and kerb alignments around the extents of the development;
  • Wider public footways;
  • New paving around the extents of the development in Artificial Stone Paving (ASP);
  • New vehicles crossovers on Harrow Road and North Wharf Road;
  • Extension of Harrow Road central island;
  • Upgraded gully works;
  • Upgraded street lighting works;
  • Resurfacing works; and
  • Changes to parking and kerbside activity.

Status

Works due

Outline Programme

Phase 1: 18/03/2019 - 19/04/2019
Phase 2: August 2019
Phase 3: Spring 2021

Project Documents

STATUS

    Concept
    Feasibility
    In Consultation
    Design Stage
    Works due
    Works on site
    Works completed