Project Overview
This project involves the implementation of two zebra crossings on Harewood Avenue, one associated with the pedestrian movements from Paribas Bank on Harewood Avenue (Phase 1) and the second associated with the pedestrian movements from Marylebone Station (Phase 2).
Both phases involve the construction of a zebra crossing across Harewood Avenue with local changes to white lining as a result. Phase 2 requires the relocation of a Barclays Cycle Hire station, which is being moved from Harewood Avenue to Boston Place.
The Phase 1 crossing has been constructed and was complete at the end of April 2014. The second crossing has also been constructed and was complete at the end of June 2015.
All works on site are now complete.
Status
Works completed