Ward: St James's
Streets Affected: Covent Garden
Project Type: Streetscape
Project Overview
On the 9th November 2015, a scheme involving the repaving of the existing northwestern
footway surfacing on Covent Garden (immediately outside and in the vicinity of St Paul’s Church) in natural York stone will commence.
This phase of works is to be completed by early December 2015.
Status
Works completed
Outline Programme
Implementation 09/11/2015-04/12/2015.
Project Documents
There are no documents available for this project