Ward: West End
Streets Affected: Brewer Street, Denman Street, Sherwood Street
Project Type: Streetscape
Project Overview
Westminster City Council is proposing footway and carriageway improvements along Sherwood Street, from the junction with Brewer Street up to Denman Street.
The improvements include the following:
- Construction of a raised carriageway table at the junction of Sherwood
- Street and Brewer Street
- Repaving and widening of footway in Yorkstone paving;
- Reinstatement of road markings;
- Asphalt resurfacing and reinstatement of granite setts on the carriageway;
- Upgrades of street lighting and drainage;
- Installation and relocation of street furniture and traffic signs; and
- Alterations and diversions of existing utilities.
Status
Works completed
Outline Programme
14th September - 5th October: footway works
5th October - 9th October: carriageway resurfacing
Project Documents
Sherwood Street - Schemeboard.pdf - (209 kb)
STATUS
On Hold
Design Stage
In Consultation
Works on site
Works completed