Ward: Church Street
Streets Affected: Capland Street, Fisherton Street, Luton Street, Salisbury Street, Samford Street
Project Type: Developer and third party funded
Project Overview
Project Overview Public realm improvement works associated with the new WCC housing development at Luton Street with frontages on Fisherton Street, Luton Street, Capland Street, Bledlow Close, Samford Street and Salisbury Street. Footway along Bledlow Close is to be paved with concrete slabs along with new lighting columns and parking configurations. New footway buildouts will be constructed along Capland Street and Samford Street to improve pedestrian accessibility. The footway along Luton Street will be paved with new concrete pavers. The footway outside 40 Fisherton Street will be paved with asphalt concrete with a new vehicular access point to parking spaces.
Status
Works completed
Outline Programme
Phase 1 - Salisbury Street and Samford Street
From 4th April - 27th June 2022.
Phase 2 - Capland Street and Bledlow Close
From 4th April - 8th July 2022.
Phase 3 - Luton Street and Fisherton Street
From 26th May - 8th July 2022