Ward: West End
Streets Affected: Sackville Street, Vigo Street
Project Type: Streetscape
Project Overview
A scheme to improve the public realm in Sackville Street & Vigo Street streets, including:
- upgrading the footway materials in natural stone
- special granite paving at northern and southern junctions
- step-free pedestrian crossings
- footway widening
- 6 new street trees
- reallocation of parking and loading
- contra-flow cycling

Status
Works completed
Outline Programme
Works on site from 31st July 2023
Two main phases of work:
Phase 1 to complete by November 2023, including Vigo Street and northern half of Sackville Street.
Phase 2 will follow on from the completion of Pegasus House development at the southern end of Sackville Street and is planned for 2025